The project is in a Balanced Matrix
environment. There are significant challenges with the
schedule and resource constraints of the project. Project personnel
have been complaining to the Project Manager about the environment. In
this type of environment, who controls the resources?
(a) Functional Manager (b) Project Manager (c) Project Coordinator (d) Senior Management |
||||
|
Resource
People, supplies, equipment, and other items used in the work of the project |
||
|
The printing company is putting a policy
in place to use just-in-time manufacturing. It feels this policy will
help minimize excess paper and ink costs and improve
efficiency in processing and maximize square footage
utilization. The amount of inventory needed for this type of process is
what?
(a) Minimal (b) 25% (c) Six Sigma (d) Zero (Correct) Explanation: The amount of inventory needed for Just in Time (JIT) inventory is zero days. This implies that inventory arrives when it is needed. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |