Crosswind Custom Websites is building an
ecommerce system. However, conflicting
priorities from other projects has delayed the finish by
two weeks. The schedule shows that the next task
is to define the requirements needed by the
customer, then that is followed by the coding. This is an
example of what?
(a) Mandatory Dependencies (b) Lag (c) Discretionary Dependencies (d) Crashing |
||||
|
Activity-on-Node (AON)
A network diagramming method in which activities are shown on the boxes or circles of the network diagram and connected via arrows |
||
|
The trade show
project team has just begun breaking down the pieces of the project
into smaller easier to maintain and
manage pieces. This is known as what?
(a) Scope Verification (b) Scope Definition (c) Scope Planning (d) Creating the WBS (Correct) Explanation: Creating the WBS process involves taking the Scope of the project and breaking it down into smaller pieces that are easier to define, estimate, and manage. Scope Verification is comparing the Scope of the project to work results. Scope Planning involves determining the Scope Statement and Scope management approach for the project. Scope Definition involves establishing the Scope Statement of the project. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |