Question of the Day
Which of the following is not likely a project resource for a software project?
A) Conference room near the team locationB) Project Manager
C) Functional manager
D) Computer programmer
Terminology of the Day
Power
The possible ability to influence behavior or performance of others
Answer and Explanation to Yesterday's Question
The Project Manager is evaluating data from a control chart and discovers nine consecutive data points on one side of the control chart. This is called what?
A) Too tight of control limits
B) A violation of the Seven Run Rule (Correct)
C) Too loose of specification limits
D) Acceptable measurements
Explanation: The Seven Run Rule is a situation in which there are at least seven consecutive data points on one side of the mean, implying that the process could have some type of problem. The other three answers are noise.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/
TEST PRODUCT AD SECTION
PMP Exam Simulation Booklet
![]() |
The PMP® Exam Success Series: Third Edition PMBOK Exam Simulation Booklet is a key tool for the future PMP® to gage their level of understanding of the complex topics covered on the exam. This allows the user to see where they are strong and where they need more help. The format of the questions and answers are set up to provide explanation of why an answer is correct or incorrect, providing increased comprehension of the knowledge needed for PMP® Exam Success. There is a complete 200 questions integrated test, not available on our other products as well as 30 questions per topic area, including framework and professional & social responsibility. |