PMHub now offers you the benefit of daily guidance to help you stay on the road to success with the project management exam or to sharpen and exercise the project management skills you already possess. Each edition of the PMHub/Crosswind Tip of the Day will give you a question of the day, daily terminology booster, and links to other helpful tools that will prepare you for exam success.
 

Question of the Day

You are the Project Manager on a medical project. You have been analyzing project data from the last two week reporting period. The main data you have been looking at involves the value of the work that should have been done, what was done, and what was paid for it. What type of report format are you looking at?


A) Status report

B)  Progress report

C)  Variance report

D)  Performance report

 

Terminology of the Day

 Kickoff Meeting

 A meeting used to initiate the start of the project; typically attended by all the key Stakeholders; can be done when initiating or planning is complete depending upon the organization

 

Answer and Explanation to Yesterday's Question

Which of the following is not likely a project resource for a software project?

A)  Conference room near the team location

B)  Project Manager

C)  Functional manager (Correct)

D)  Computer programmer

 Explanation: Resources can be anything that helps contribute to a project's success. No disrespect toward Functional Managers, but the other answers are clearly better examples of project resources that are used directly on a project. The functional manager might be involved in the project but usually in only controlling resources.

For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/