In evaluating contracts there are a number of components that make a contract enforceable. All of the following items are needed to make a contract legal except_____.
A) An offerB) Legal purpose
C) Negotiation
D) Consideration
Terminology of the Day
Project Procurement Manag
The process of attaining goods and services for a project from outside the organization
Answer and Explanation to Yesterday's Question
On the electric company project the government implemented a regulatory change associated with the electricity sub-station upgrade project that required the company to spend an additional $400,000 US on the project. This type of cost and activity best relates to which of the following?
A) Known unknowns
B) Unknown unknowns (Correct)
C) Management Reserve
D) Risk Management
Explanation: Management Reserves are created for unknown unknowns. These are things that wouldn't be expected to happen. Contingency Reserves are created for known unknowns. These are things that we know will happen, we just don't know how much of it will happen. Risk Management is noise.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/
TEST PRODUCT AD SECTION
PMP/CAPM Exam Success Series Processes Audio CD
![]() |
The PMP®/CAPM® Success Series: Understanding the Processes Audio CD is a key tool for anyone preparing for the PMP®/CAPM® exam. This CD has descriptions of all 44 processes covered on the PMP®/CAPM® exams. The format describes each of the processes, where they occur and have impact, as well as a description of the process and key inputs, tools, and outputs. It's perfect for memorizing how all the pieces of the PMBOK® Guide fit together during that long commute to the office or that late night study session. |