Welcome!
Question of the Day
You are a Project Manager who is involved in the procurement of police cars and security equipment for the city government you work in. As negotiations begin between the city and the vendor, you realize that your brother works for this company but in a different department. What is your professional responsibility?
A) Because he works in a different department, you can remain on the project.B) Remain on the project, but remove yourself from the negotiations.
C) Remove yourself from the project.
D) Remain on the project, but help another Project Manager negotiate the contract.
Terminology of the Day
Confidentiality
The act of not providing certain confidential information to those that should not know about it
Answer and Explanation to Yesterday's Question
The retail chain is using a vendor to provide engineers for a security camera network design and implementation. The team has been completing the work they agreed upon. Both parties are communicating via status reports. The seller has submitted the first payment request. In what process is the team involved?
A) Plan Contracting
B) Request Sellers Responses
C) Contract Administration (Correct)
D) Select Sellers
Explanation: Contract Administration involves managing the contract. Plan contracting involves determining the approach to find a company who can do the work for you. Request sellers responses involve receiving and reviewing proposals from companies being considered for the work. Select sellers involve choosing the company to do the work.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/
TEST PRODUCT AD SECTION
PgMP Exam Review Processes Audio CD
![]() |
The PgMP (SM) Exam Review: Processes Audio CD is a key tool for anyone preparing for the PgMP (SM). This CD has descriptions of all 36 process areas covered on the PgMP® exam. The format describes each of the processes, where they occur and have impact, as well as a description of the process and key inputs, and outputs. It's perfect for memorizing how all the pieces of the PMI Standards fit together during that long commute to the office or that late night study session. |