
Welcome!
Question of the Day
Which of the following represents a rule of thumb associated with the WBS decomposition process?
A) Breakdown the work of the project until it is done by a single resourceB) Using an organizational structure appearance
C) Creating a WBS where the summary tasks are equal to the detail underneath it
D) Breaking work down to realistic level where work packages are the lowest level
Terminology of the Day
Scope control
The process of controlling the Scope of the project
Answer and Explanation to Yesterday's Question
The functional manager and Project Manager are arguing about the project management plan and what is needed to create it, as the functional manager is short on resources. Which of the following is the best to create the project management plan?
A) Project Manager
B) Project Manager and team (Correct)
C) Team
D) Sponsor
Explanation: The Project Manager and team are the best selection to create the project management plan and the estimates that feed into it. They are the people doing the work, so they should have the opportunity to estimate and plan it as well as possible. The Sponsor pays for the project. The Project Manager or the team only wouldn't be a good choice as both are needed for a realistic plan.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/
TEST PRODUCT AD SECTION
PgMP Exam Review Terminology Audio CD
![]() |
The Pgmp(sm) Exam Review: Terminology Audio CD is a key tool for anyone preparing for the PgMP(sm) Exam. This Audio CD has Terms and Definitions for all 36 processes covered on the PgMP(sm) Exam. The format allows you to listen to the term, think of the answer, and then hear the correct answer. It's perfect for quizzing yourself or memorization during that late night study session, or that long commute to the office. |