Question of the Day
All of the following are examples of communication infrastructure that a Project Manager could encounter on a project except ______
A) Conference roomsB) Spreadsheet applications
C) Intranet site
D) E-mail system
Terminology of the Day
Exception Report
A report that includes significant variations from the planned activities
Answer and Explanation to Yesterday's Question
The construction project has some challenges. The Project Manager has continually had to tell the team what to do. The team members also do not seem to trust management that much and often appear unmotivated. This is an example of what?
A) Bad performance
B) Theory X environment (Correct)
C) Forcing
D) Theory Y environment
Explanation: A theory X environment typically will have employees having to be told what to do, having distrust for management, and lacking motivation. Theory Y is the opposite. The other two answers are noise.