PM Hub now offers you the benefit of daily guidance to help you stay on the road to success with the project management exam or to sharpen and exercise the project management skills you already possess. Each edition of the PM Hub/Crosswind Tip of the Day will give you a question of the day, daily terminology booster, and links to other helpful tools that will prepare you for exam success.
 
Question of the Day
The Project Manager has just received the charter. He is preparing an initial estimate called an order of magnitude (OOM) estimate. What is the range of an order of magnitude (OOM) estimate?

A) -10% to +5%
B)  -5% to +10%
C)  -25% to +75%
D)  -300% to +75%
 
Terminology of the Day
 Cost Variance (CV)
 Difference between what has been built (EV) and the cost to build it (AC); Formula: EV-ACA value of zero means the project is creating what it should for the cost as planned. A negative value means over budget, a positive value means under budget
 
Answer and Explanation to Yesterday's Question
In the original Network diagram question, if Task D increases from five to eight days, what is the Critical Path, and what is the length?
A)  ACFH, 16 days
B)  BCFH, 18 days
C)  BDFH, 20 days
D)  BDGH, 21 days (Correct)
 Explanation: By increasing Task D from five days to eight days the path BDGH increases to twenty one days. This is the longest of the paths on the Network diagram.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/
 
TEST PRODUCT AD SECTION
Exam Review and Best Practices Calendar
Double-sided laminated calendar
Reusable from year to year (It never expires)
Study for the PMP® Exam every day with full answers and explanations
Master best practices for project managers every day with relatable areas of project management
http://www.crosswindpm.com/cart/index.php?p=product&id=64&parent=74