Welcome!
Question of the Day
The Project Manager is planning how many people he will need on the construction project. This will more than likely require more than one person with each skill set. He is reviewing the level of effort of each skill set that are needed each month on the project. What will he likely use to visually represent this data?
A) Resource HistogramB) Responsibility Assignment Matrix (RAM)
C) PERT chart
D) Pareto diagram
Terminology of the Day
Project Team Directory
A list of all project team members, their project roles, and their communication needs as they relate to the project
Answer and Explanation to Yesterday's Question
The team is in the process of planning what quality standards are needed on the project and how to achieve those standards. The team members are evaluating what could potentially cause issues in achieving these standards. Which of the following are they most likely to use to accomplish this goal?
A) Pareto diagram
B) Quality Audit
C) Control chart
D) Fishbone diagram (Correct)
Explanation: The Fishbone diagram can be used to look for problems that could show up on the project. The Pareto diagram is used to show the frequency of defects. The Control chart shows output over time. A Quality Audit helps ensure that the project will meet the quality needs.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/
TEST PRODUCT AD SECTION
PMP Certification Exam Manual and Exam Simulation CD-ROM Combo
Pack
![]() |
The
PMP® Exam Success Series: Certification Exam Manual is the
foundation
of the PMP Exam Success Series (currently used in 33 countries). This
is a must have for anyone preparing to take the PMP® Exam. This
book is
complete with valuable exam preparation information, including
"Crosswind Must Knows" for each exam topic, terms and definitions,
formulas, exercises (matching, Earned Value and Network Diagram
Analysis) and situational questions translation. |