Question of the Day
The retail chain is using a vendor to provide engineers for a security camera network design and implementation. The sellers are receiving a very detailed description of the work that is anticipated to be involved in the project. What type of Scope of Work is being provided to the sellers?
A) FunctionalityB) Design
C) Analogous
D) Cost Plus
Terminology of the Day
Project Procurement Manag
The process of attaining goods and services for a project from outside the organization
Answer and Explanation to Yesterday's Question
The software company has been awarded a $100M US contract to build an enterprise application for the military. The company understands that there is a small company that has a product that complements theirs that the military will likely need to work with as well. The software company decides to acquire the complementary company to offer a more complete solution to the military. This is an example of what type of risk response strategy?
A) Exploit (Correct)
B) Share
C) Mitigate
D) Accept
Explanation: Exploiting the risk is to do things to grow or expand the positive aspects of the risk. Sharing the risk is to work with someone else to maximize the risk. Mitigate would attempt to minimize the bad or maximize the good impact of the risk. Accepting the risk would be to tolerate whatever happened.