
Welcome!
Question of the Day
The project is using a new auto press machine that cost $50,000 US. The Project Manager is told to set up depreciation for the server over a five-year schedule, with the auto press having a value of $0 at the end of five years. Standard depreciation will be used in the calculation. What is the amount per year the server will depreciate?
A) $10,000 USB) $5,000 US
C) $2,500 US
D) Not enough information
Terminology of the Day
Definitive Estimate
A Cost Estimate that provides the accurate estimation of the project costs; the final estimate to be used on the project before implementation begins
Answer and Explanation to Yesterday's Question
Float on a Network diagram is also known as:
A) Lag
B) PERT
C) Slack (Correct)
D) GERT
Explanation: Slack and Float are interchangeable terminology. Lag is a delay between tasks on a Network diagram. GERT and PERT are noise.
For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at http://www.crosswindpm.com/