|
|||
|
In Risk Management, the Risk Register
contains a number of items. Risks and triggers are two of the items the
Project Manager will reference from the risk register. In evaluating a
Risk Trigger, which of the following is most accurate?
(a) A trigger is an indicator that a risk event will occur (b) A trigger is the same as a risk. (c) A trigger is an indicator that a risk event has occurred. (d) A trigger is an indicator that a risk event could occur. |
||||
|
Buffer
Compensation in the planning for unknown items that could occur. This is typically schedule or cost related |
||
|
All of the following would be good
reasons to cancel a meeting except?
(a) The agenda wasn't published until right before the meeting. (b) A key team member had to attend a different meeting. (c) A Functional Manager wanted to meet with the Project Manager at the same time.(Correct) (d) The topic partially changed and the presentation material wasn't complete yet. Explanation:The Functional Manager wanting to meet with the Project Manager at the same time as an existing team meeting wouldn't be a good reason to cancel a meeting. The Project Manager should offer to schedule a meeting for a different time with the Functional Manager. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |