Configuration management involved which of
the following as related to project management?
(a) A thorough Change Control System to ensure the project produces the desired results (b) A system used to store versions of software code (c) A system used to store versions of documentation on a project (d) A piece of an automated Project Management system used to set up project variables |
||||
|
Change Request
A request to change something on the project |
||
|
Which of the
following is an example of a standard?
(a) 700MB capacity for a CD-ROM. (Correct) (b) The number of slides in your last presentation (c) The shade of paint selected to paint your office (d) The average speed that someone drives to work Explanation: A standard is a measurement for something that is consistent and generally accepted. In this case, the capacity of a CD-ROM is the only "standard" listed in the answers. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |