Crosswind Custom Websites is building an
ecommerce system. However, conflicting
priorities from other projects has delayed the finish by
two weeks. The schedule shows that the next task
is to define the requirements needed by the
customer, then that is followed by the coding. This is an
example of what?
(a) Mandatory Dependencies (b) Lag (c) Discretionary Dependencies (d) Crashing |
||||
|
Activity Sequencing
The process of determining and documenting the logical relationships between activities or tasks on the project |
||
|
The trade show
project team has just begun breaking down the pieces of the project
into smaller easier to maintain and
manage pieces. This is known as what?
(a) Scope Verification (b) Scope Definition (c) Scope Planning (d) (Correct) Creating the WBS (Correct) Explanation: Paste Explanation Here For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |