PMHub now offers you the benefit of daily guidance to help you stay on the road to success with the project management exam or to sharpen and exercise the project management skills you already possess. Each edition of the PMHub Tip of the Day will give you a question of the day, daily terminology booster, and links to other helpful tools that will prepare you for exam success.
PMP terms and def audio cd
The PMP® Success Series: Terms and Definitions Audio CD is a key tool for anyone preparing for the PMP® Exam. This CD has Terms and Definitions for all 44 process areas covered on the PMP® and CAPM® Exams. It is designed for minimal study time. The format allows you to listen to the term, think of the answer, and then hear the correct answer which helps to maximize memorization. It's perfect for quizzing yourself or memorizing during that late night study session, or that long commute to the office.

Question of the Day

The project is in the process of determining the accuracy of the work of the product. The project team members are utilizing a progressive elaboration approach. They discover that the process to measure the output is not going to produce the results needed. What process will fix the problem?

(a) Perform Quality Assurance
(b) Perform Quality Control
(c) Quality Planning
(d) Quality Management

Terminology of the Day
Cost of Nonconformance

Accepting responsibility for not meeting quality expectations of the project or product
Answer and Explanation to Yesterday's Question
Task A is worth $400, is 95% complete, and actually cost $395. Task B is worth $350, is 90% complete, and actually cost $330 so far. Task C is worth $275, is 100% complete, and has cost $310 so far. The total budget is $2500. What is the Variance at Completion for the tasks listed?

(a) -$168.09
(b) $2500
(c) $2668.09
(d) $1633.09

Explanation: The Variance at Completion (VAC) is the difference between the Budget at Completion (BAC) and the Estimate at Completion (ETC). To calculate this, subtract $2500 (BAC) from $2668.09 (EAC) for a difference of -$168.09 US.