The project is in the process of determining the accuracy of the work of the product. The project team members are utilizing a progressive elaboration approach. They discover that the process to measure the output is not going to produce the results needed. What process will fix the problem? (a) Perform Quality Assurance (b) Perform Quality Control (c) Quality Planning (d) Quality Management |
||||
|
Cost of Nonconformance
Accepting responsibility for not meeting quality expectations of the project or product |
||
|
Task A is worth
$400, is 95% complete, and actually cost $395. Task B is
worth $350, is 90% complete, and actually cost $330
so far. Task C is worth $275, is 100% complete, and has cost $310 so
far. The total budget is $2500. What is the Variance at Completion for
the tasks
listed?
(a) -$168.09 (b) $2500 (c) $2668.09 (d) $1633.09 Explanation: The Variance at Completion (VAC) is the difference between the Budget at Completion (BAC) and the Estimate at Completion (ETC). To calculate this, subtract $2500 (BAC) from $2668.09 (EAC) for a difference of -$168.09 US. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |