The Project Manager has just completed
determining with assistance from the team
what will be done as a result of uncertain events
happening on the project as well as who will be
responsible for monitoring and responding if the events do
occur. Which of the following best describes what
they have just completed?
(a) Risk Identification (b) Risk Response Planning (c) Secondary Response Planning (d) Qualitative Analysis |
||||
|
Fallback Plans
A type of plan created for risks with a great impact on project goals, to be executed if attempts to minimize the risk are not successful |
||
|
The Project Manager
is in the process of communicating to the team the
tasks, their sequence, durations, and who is responsible for doing what
work on the project. Which of the
following contain this information?
(a) Schedule (Correct) (b) Gantt chart (c) Work Breakdown Structure (d) Responsibility Assignment Matrix Explanation: This is the schedule. It consists of the Gantt chart and Work Breakdown Structure (WBS) among other items. The Responsibility Assignment Matrix shows who is responsible for what areas on the project. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |