The electrical crew discovers that an
additional circuit is needed to supply the appropriate
electricity to the new injection molding machine at the plastic
factory. This circuit will be only used on
this machine, and only products from the kiwi product line
will be made on the machine. What type of cost would
this be to the product line?
(a) Direct (b) Indirect (c) Variable (d) Indirect fixed |
||||
|
Code of Accounts (Tool)
A numbering system used in project management to identify pieces of the Work Breakdown Structure |
||
|
Calculate the standard deviation for the
following: Pessimistic=14, Optimistic=6, Realistic=8.
(a) 1.33 (Correct) (b) 1.78 (c) 8.66 (d) Not enough information Explanation: The formula for standard deviation is Pessimistic-Optimistic divided by 6. The answer is 1.33. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |