PMHub now offers you the benefit of daily guidance to help you stay on the road to success with the project management exam or to sharpen and exercise the project management skills you already possess. Each edition of the PMHub Tip of the Day will give you a question of the day, daily terminology booster, and links to other helpful tools that will prepare you for exam success.
placemat
The PMP® Exam Success Series: Certification Exam Placemat Volume 2 is an 11 * 17 inch placemat with a double-sided protective laminate casing. This placemat contains process mapping, knowledge areas, tables and formulas organized for fast and easy memorization. This product also contains outputs mapping to compliment Placemat Volume 1. The illustrations for all 9 knowledge areas are color-coded. This very accessible format makes the PMP® Exam Success Series: Certification Exam Placemat Volume 2 perfect for last minute study sessions.

Question of the Day
The Department of Defense is involved in performing risk reviews as part of their overall risk strategy. Which of the following best describes Risk Reviews?

(a) Determining what risks are on the project
(b) Determining what the characteristics of the risks are on the project
(c) Determining the validity of the documented risks and looking for any new risks that could occur
(d) Determining who will implement a Risk Response Plan

Terminology of the Day
Monte Carlo Analysis

A technique used to simulate the outcome of a project many times, to determine the range of possible outcomes and the probability of their occurrence
Answer and Explanation to Yesterday's Question
The project is approximately 70% complete and in the middle of execution. The Project Manager is communicating with Stakeholders regarding the status of the project. Which is he likely to use to ensure proper communication is delivered?

(a) Information Retrieval Systems
(b) Communications Management Plan (Correct)
(c) Formal communication
(d) Verbal communication

Explanation: The Communications Management Plan is used to help determine what the Stakeholders communication needs are. The other answers are noise.

For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com