This is an interesting conversation on critical path calculation methods - in particular ES and LS. Mahendran asked the questions and Mike Newell (noted PMP book author) and Dr PD Giammolvo provided the answers

Mmahendran,

 The question is regarding the method to be adhered to calculate Early Start(ES) and Late Start(LS).

  a) In some books(Rita Mulcay) the ES of
the first activity is taken as 0(zero) and early finish is
calculated as ES + duration = Early Finish

  b) In some books(Head First) the ES of
the first activity is taken as 1(one) and the early finish
is calculated as ES + duration - 1 = Early Finish.


When the question is regarding "What is the ES of an
activity". Both the books give different answers.

The answer in the first book is X and the second book is
X+1.  Could any body please clarify which is correct.


Mike Newell answer:


There is a convention that all schedulers use if they are working in days and most schedules are in days.  Some are not. in days then.  All activities start on the morning of the day they start and end on the afternoon of the day they finish.  Thus, if an activity took one day, it would start on, say, March 14, in the morning, and it would finish on March 14, in the afternoon, and from morning of the day to afternoon of the same day is one day duration.

If you are scheduling in hours for example, the clock method is used.  This says that if an activity takes one unit of time, in this case an hour, you think of the hands of a clock.  In one unit of time you go from 12 o'clock to one o'clock and the next unit starts at one o'clock.

So, you see both methods are used.  If time units are days, you use one method and if you are using any other time unit, you use the clock method.

Incidentally, Microsoft Project does it this way.  Try it.

Try not to memorize formulas, reason things out and you will remember them long after the exam.

If you want, contact me at mnewell@psmconsult.com

Colleagues,

As a follow on elaboration to Mike's answer, starting the clock running at
zero is used by ADM or Activity on Arrow (AoA), while the clock starting to
run on the morning of day 1 is the convention used by PDM or Activity on
Node (AoN).


You will find that Primavera, MSP and nearly all other software today uses
PDM. (I am unaware of ANY major software that uses the ADM or AoA method)  I
BELIEVE, (but am not 100% certain) that PMI mercifully killed off ADM/AoA
and I would hope that AACE and other professional organizations do likewise.


Not to date myself, but for back ground information the last time I used ADM
professionally on a project was in 1979-1982 on the Negev Airbase Project,
Ovda, Israel. We were running a program called MSCS and to give you some
idea just how long ago that was, we were updating the schedule monthly using
PUNCH CARDS.

When Primavera went from being DOS based to Windows, they killed off the
option of using ADM or PDM, and use PDM only now for many years.

To my knowledge, ADM/AoA only exists in textbooks these days..


BR,

Dr. PDG, in Boston

Comments

Name *
Email (For verification & Replies)
Code   
ChronoComments by Joomla Professional Solutions
Submit Comment
Last Updated on Saturday, 26 March 2011 19:56
 

PMP Exam Simulator

Test drive your PMP Exam before the real exam - you can practice as many times as you need to. Click the graphics below
Banner
Didn't Pass The PMP Exam? Get 90 More Simulator Days! This offer is valid for all customers of The PM Exam Simulator. To claim the 90 day free extension customers must send a copy of their Exam Score Report to support@pm-exam-simulator.com within 45 days of their exam attempt. The support team will extend the simulator by 90 days starting from the day that the Exam Score Report was received.

Short Guide to becoming a PMP

Watch a FREE Video and dowload a short manual: Short Guide to becoming a PMP - click THIS

Share Articles with Friends & Colleagues

To share articles with your friends and colleagues, just hover your mouse cursor on top of the SHARE box just below the Title of the article.
For Linkedin, click the box named in SHARE
Happy sharing and thank you for visiting PMHUB Today !

Joseph Phillips PMP Prep

 Joseph Phillips Course: 35 contact hours 200 PMP exam questions. All for ONLY $55. For more info- Click here to view more details

jp


 

PMP Study Coach

Are you studying for the PMP® exam and you don't know how to get started? Are you unsure about what and when to study? Let The PM StudyCoach be Your Roadmap for the next 10 weeks.

The PM StudyCoach is a 10-week long course. At its center are the 12 Coaching Sessions with your coach Cornelius Fichtner, PMP.

Please click here for more info: HERE


PMHUB Amazon Shop

Banner

PM Prepcast

Best Value PMP product and the PMHUB all time best seller
Banner
March 2010: More than 13,000 PMPs buy this highly rated study material PMHUB is an affiliate of The PM PrepCast (a PMI REP) and earn a referral commission

PMP Formulas

PM Formulas - formula for success in PMP Exam
Banner

PMP Flashcard

eFlashcard
Banner

{RUN_CRON_TASK}