PMPrepcast – the PMHUB best seller

Prep On June 1, 2010 more than 10,000 PMP aspirants passed the exam with PMPrepcast.


To order, click THIS.

To compare the 4 PMPrepcast products  and to check which ones are the most suitable for you, please click this link HERE
 PMHUB is an affiliate of The PM PrepCast (a PMI REP) and earn a referral commission

A New Way to collect your PDU

Great news! PMPODCAST now offering a 10% discount for The PDU Podcast(TM) Yearly Subscription. You can avail of this if you subscribe to it today until August 31, 2010. The coupon code for this promo is 10pducast.

PM StudyCoach – PMP in 10 weeks & $34.99

Are you studying for the PMP® exam and you don't know how to get started? Are you unsure about what and when to study? Let The PM StudyCoach be Your Roadmap for the next 10 weeks.

The PM StudyCoach is a 10-week long course. At its center are the 12 Coaching Sessions with your coach Cornelius Fichtner, PMP.
Please click here for more info: HERE

To compare the 4 PMPrepcast products  and to check which ones are the most suitable for you, please click this link HERE
 PMHUB is an affiliate of The PM PrepCast (a PMI REP) and earn a referral commission

PM Formulas (PMBOK 4th ed)

formulaFormula for your Exam Success - only $29.97. To Order, click THIS PMHUB is an affiliate of The PM PrepCast (a PMI REP) and earn a referral commission

For REGISTERED Blog Members

To download FILES, please click

Download folder

PM eFlashCard (PMBOK 4th ed)

flash$29.99
To Order, click HERE PMHUB is an affiliate of The PM PrepCast (a PMI REP) and earn a referral commission

Categories

Sitemeter

PMP Study Materials

Exam Study Materials

Getting PMP through your Ipod!
Best value for Money. $99.99 for a complete PMP Exam Preparation course. 35 Contact Hours. Cover complete PMBOK and all other Exam topic. PMHUB all time best seller
PMP Exam Tip and Tricks
Want to know the secret of passing the PMP, PgMP, CAPM certification?
PMBOK 4th ed Study Materials
Newly published Study Materials based on PMBOK 4th edition
Free 500+ PMP Exam Question
Great Resource for PMP, PgMP, CAPM Certification Exam. 500+ Exam simulation questions & answers. No need to register.
Ratings & Review of PMP Study Materials
Reviews and Ratings of 9 most popular study materials
PMHUB Study Notes & Tools
Free PMP Exam Study Notes & Tools, including game. Proven tools of study to thousands of PMs
Best 6 LLs from 2001-2009
Here is arguably the best 6 LLs -selected from more than 1,000 Lesssons Learned in PMHUB archives
User:
Password:

| Register | Lost password?

1,135 views

Joseph Phillips, PMP: Estimating Time and Project Resources

josephphillipsOnce the WBS has been created the project manager and the project team can begin to create an estimate of how long the project work will actually take and what resources are required to complete the project work. Resources are generally thought of as people and the roles they play within a project (think network engineer, mechanical engineer, and architect). Resources, however, are also things like materials, equipment, and facilities that the project needs in order to be successful.


When the project manager first begins to estimate the duration of the project she should always look for historical information. If a project of this type has been completed before historical information will be the best input to the project duration estimating process. This approach is also known as analogous estimating – where the project manager is creating an analogy between the two projects. When using an analogous estimate the projects don’t, and often won’t, be identical. It’s an estimate based on projects that have completed in the past.

Real World Note: An analogous estimate is also known as top-down estimating. It’s not a very reliable estimate, but it’s a quick way to estimate the project duration.

Another project duration estimating approach is the parametric estimate. This estimating technique uses a parameter to determine how long the project work should take to complete. For example, a project to install 80 printing presses may estimate that one printing press will take 35 hours to install, so the parametric estimate would be 80 times 35 hours for 2,800 of labor.

This approach is somewhat reliable, assuming that the initial parameter used is reliable. A parametric estimate does not take into account the learning curve. Basically, when it comes to estimating time using a parametric estimate, the more times a person does an activity their efficiency at repeating the activity will increase, so the duration to complete future activities will diminish.

Consider a project to paint 4,000 hotel rooms. Rooms 1-10 may be somewhat slow but after a project team paints room 40, or 50, or even 100 their efficiency at doing that type of work will increase, so the parametric estimate would be flawed. As you can guess, the parametric estimate is a quick but somewhat unreliable approach to project time estimating.

Some project managers use what’s called a three-point estimate to predict how long the project duration will take. This estimate type uses three points for each work package: the optimistic estimated >time, the most likely estimated time, and the pessimistic estimated time to predict how long each work package will take to complete. The project manager then finds and uses the average of the three points to estimate how long the project work will take to complete. Figure 4 is an example of the three-point estimate in action.

Figure 4: A three-point estimate finds the average time for each activity duration .


Real World Note: The Program Evaluation and Review Technique (PERT) is similar to the three-point estimate. PERT uses a weighted average while the three-point estimate does not. Here’s the formula for PERT: (Optimistic + (4 x Most Likely ) + Pessimistic)/6.


Guess what? It’ll magically take 40 hours to complete the work. Suzie will either complete the work in 32 hours and not tell you she’s done because she reported it’ll take 40 hours or she’ll ease through the work and use all 40 hours to complete the 32-hour assignment. Another possibility is that Suzie won’t start on the actual work until hour eight and she’ll pray and hope nothing goes awry in the assignment. The worst possible scenario is that she’ll wait until hour eight to begin, things do go awry, and she’ll require more than the allotted 40 hours for the work.


There are multiple strategies to combat Parkinson’s Law, one of which is the three-point estimate. Another approach is to use a “management reserve” which is a pool of time that all activities may borrow from should their activities go over the allotted completion time. In other words, if a project is estimated to take ten months to complete the project manager will allot approximately 15% additional time for management reserve. The project will, in this instance, take eleven and a half months to complete. As activities are late the time is subtracted from the management reserve. To use management reserve, however, the project manager and the project team must agree to be accurate and as honest as possible when estimating how long activities may take to complete.


Sometimes it’s darn near impossible to use management reserve – or to provide an accurate time estimate. This is true if a project of this nature has never been attempted before. When a project has never been attempted before it’s called “The First-Time First-Use Penalty.” If you’ve never tried to use a particular type of material, create a particular type of software, or install a new appliance you likely won’t know how long it’ll take to complete the work until you actually get in and complete the work. It’s kind of like the first person that decided to eat a snail – he didn’t know they were tasty until he ate one.


Real World Note : The First-Time First-Use Penalty is one of the reasons why it’s critical to future project success to keep a lessons learned document and accurate project records of actual time and costs to complete the project work. You’re creating future historical information so other projects can glean from your experience.


  • Share/Bookmark

Related posts:

  1. Joseph Phillips: The Technical Side of Project Management
  2. Joseph Phillips: Defining the Project Life Cycle
  3. Joseph Phillips: How Projects Get Done

Leave a Reply

 

 

 

You can use these HTML tags

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

genericos viagra curare impotenza