THIS MONTH SPECIAL

BUNDLE: PM Prepcast & Exam Simulator

The PM PrepCast & The PM Exam Simulator Bundle is now only at $206.99, instead of paying the regular price of $229.99. Use the coupon code Jul14. This offer is good from July 1-31, 2014 only.

Pls click this LINK

Watch this short video: http://www.youtube.com/watch?v=8tG81gp6AuQ for instruction on how to apply the coupon code.

The PMHUB best-sellers

PMPrepcast More than 25,000 PMP aspirants passed the exam with PMPrepcast.

PMP Exam Simulator

Test yourself exhaustively before the PMP Exam



PMP Practice Exam System

Agile Prepcast

Whizlabs provides 3 chapters of its PMI-ACP book FREE for your evaluation HERE

If you are satisfied - keyin PMHUB10 as your coupon code to get 10% OFF here:PMI-ACP Self Study Training

A New Way to collect your PDU

Simple & Affordable PDU , view VIDEO Click for more INFO

PM Formulas

PM Study Coach

The PM Study Coach is your GPS to the PMP Exam. Over the course of 10 weeks you will receive a series of 14 recorded coaching sessions and supplemental study materials. In this way you follow a proven study approach that thousands have followed before you. You'll know exactly what to do. Day after day. Week after week. Pls click this LINK

PM Perfect Class

Virtual PMP Classes

David Kohrell PMP: PERT Formula

Number of View: 29415
PERT - 3 POINT Estimate

3 Point Estimate with 3 people

The Program Evaluation and Review Technique (PERT) formula is a simple and useful tool for project managers, and those who are planning to take their PMP Exam should have it memorized. There is much more to PERT as a project scheduling and planning technique than this formula, but here we’ll focus just on the formula.

The PERT formula is mentioned in the 4th edition PMBOK® as a tool and technique of two processes—Estimate Activity Durations and Estimate Costs. The formula provides a weighted estimate—and the formula doesn’t care if the numbers you use represent time or money—so that’s why it’s in both the PMBOK’s Time and Cost knowledge areas.

To use this formula, we need three estimates—Optimistic (best-case scenario), Most Likely (realistic), and Pessimistic (worst-case scenario). We then find the average, but we first weight the Most Likely estimate by 4. The formula is (O + (4*ML) + P) / 6. We must divide by six because we in effect have six different estimates (although three of these estimates are the same number). We are averaging (O + ML + ML + ML + ML + P) / 6.

Here’s an example. The Estemitte family is driving home. They guess they are most likely 10 minutes from home, so that is their Most Likely estimate. If all the lights turn green, they guess it may take just 7 minutes to get home, so that is their Optimistic estimate. If it starts raining hard, they guess it may take them 12 minutes to get home, so that is their Pessimistic estimate. We simply put these numbers into the formula: (7 + 10 + 10 + 10 + 10 + 12) / 6 = 9.83 minutes.

This formula is most useful in estimating time or cost of activities for projects that are especially unique, such as in research and development where there are many unknowns. For projects that are similar to previous projects and there is good historical data and expert experience, the formula is less useful.

David Kohrell, PMP, CBAP, CISA, Seminar Leader, TAPUniversity, Consultant and President, Technology As Promised, LLC (TAP)

http://blog.tapuniversity.com